Road works

For updates on the current works, please consult CITA.

From 15th March: road closure on the rue de Dommeldange CR 233 due to works by CREOS

The installation of a new underground medium-voltage power line between the Heisdorf substation and Dommeldange requires the closure of Rue de Dommeldange.

Phase 1: The road is closed to all traffic except residents and suppliers. Access to the Hostellerie Stafelter restaurant is guaranteed.

Phase 2: Traffic will be regulated by traffic lights between the PN16 level crossing and the border of the municipality in the direction of Beggen from 26 August until the end of the construction work (approximately January 2025).

End of May: completion of the road works on the Route de Luxembourg N7

The works for the final layer of pavement will be carried out in three phases, from 22nd to 28th May.

During all three phases, traffic will be controlled by traffic lights.
During phase 3 (in green), access to Rue Cité Grand-Duc Jean will be closed during the works on 27th and 28th May.